The inverter is an Eco-Worthy 10KW unit which, like many others you can buy, is just a re-badged SRNE inverter.
It’s got two MPPT channels, and the PV input voltage range is 100-500v DC.
I’m planning the layout and wondering if I can have my main string of 12 south-facing panels in series going to MPPT1 at 288 volts and a secondary string of 8 panels going into MPP2 at 192 volts. Trying to make the most of my limited west and south-facing roof real estate.
I can definitely ask the manufacturer support, but figured this was a basic enough question I’d ask here first and possibly get an answer faster.
Yes, that’s the main purpose of having 2 inputs.
That’s what I assumed but wanted to be 100% sure before i committed to two different sized strings. Thanks!